Dukhan Highway (west contract) - pavement works
By Bahrain Asphalt
Qatar · 2009
- Role
- Pavement works (asphalt and sub-base)
- Scale
- About 42 km of new highway; 1.7 million tons of asphalt and 930,000 tons of sub-base
Haji Hassan Group (HHG)
Haji Hassan Group (HHG) is a family-owned Bahraini construction materials and contracting group. It traces its start to 1952, when the late Haji Hassan Al A'ali ran a small manual stone-crushing plant, and it is still led by his family. Over the following decades it added block making, a construction department, asphalt, ready-mix and precast concrete, steel reinforcement, cranes, pipes, tanks and insulation products, and it also owns housing compounds and shopping centres.
The group presents itself today as 14 companies. Bahrain Asphalt, set up in 1965, is its roads and paving contractor; most of the other companies make or supply materials - Haji Hassan Readymix, Bahrain Blocks, Bahrain Precast Concrete, Haji Hassan Reinforcements, Bahrain Pipes, Bahrain Tanks, KRAH Bahrain and Isola - alongside Haji Hassan Cranes, a property arm and newer units such as Evolve and Aba'ad Construction.
Its published references span Bahrain's causeways, the airport, highways and landmark buildings, plus precast work in the UAE, Qatar and Oman. In most of them the group companies supplied materials; the road and paving jobs were carried out by Bahrain Asphalt.
| Role | Construction group |
| Legal form | B.S.C. (closed), as registered |
| Sectors | Roads and infrastructure, construction materials, property |
| Services | Asphalt and road works, ready-mix concrete, concrete blocks and paving, precast concrete, steel reinforcement, pipes and tanks, insulation and waterproofing products, crane hire, mechanical engineering workshop, property |
| Founded | 1952, Bahrain - started as a manual crushing plant |
| Founder | The late Haji Hassan Bin Ali Al A'ali |
| Group companies | 14, as the group states |
| Chairman | Jalal Al Aali |
| Ownership | Family group - managed by the founder's descendants, as the group states |
| Markets | Bahrain; precast and asphalt references in Qatar, the UAE and Oman |
| Supply references | About 70 references on the group's projects page, most of them material supply (ready-mix, blocks, reinforcement, precast, pipes, insulation) by group companies - among them The Avenues, Bahrain Marina, Marassi Terraces, Bahrain City Center, Four Seasons Hotel, Bahrain International Circuit and Bahrain International Airport |
| Recent recognition | Green Factory 2025 certification for Haji Hassan Ready Mix Concrete Company, as the group reports |
By Bahrain Asphalt
Qatar · 2009
By Bahrain Asphalt
Jasra, Bahrain · 2023
By Bahrain Precast Concrete (BPC)
Jasra, Bahrain
By Bahrain Asphalt
Zallaq, Bahrain
By Bahrain Asphalt
Bahrain
Electricity and Water Authority (EWA), Bahrain
Licensed plumbers list
| Listed as | Alhaj Hassan Group B.S.C Closed |
See the list · Checked 21 Nov 2026
Tender Board, Kingdom of Bahrain - monthly awarded-tenders reports (public-record contract awards, not a register)
Awarded tenders (monthly reports)
| Listed as | Alhaj Hassan Group B.S.C Closed |
See the list · Checked 23 Nov 2026
Named in Tender Board of Bahrain monthly awarded-tenders reports
| Contract | Year |
|---|---|
| RDS-15/0008 - Term contract for civil works (2015-2017) - Ministry of Works - BHD 226,000 (change order) | 2018 |
| HP/23/16 - Infrastructure works for 862 housing units and 16 residential buildings, sites 221 and 222, block 960, Muruj Al Dur - Ministry of Housing - BHD 9,080,000 | 2017 |
| RDS-15/003 - Upgrade of the Jasra junction - phase one - Ministry of Works - BHD 429,465 | 2016 |
| BAC/158/2015 - Infrastructure works for the fuel station on the airport apron, Bahrain International Airport - Bahrain Airport Company - BHD 218,635 | 2016 |
| RDS-15/0017 - Road projects - GCC Development Programme for Bahrain - Northern City entrance road improvement projects - approval… - Ministry of Works - BHD 7,698,990... | 2016 |
| HP/03/16 - Infrastructure works for 21 A-ANAD-type housing units, site 226, block 732, Aali - Ministry of Housing - BHD 221,163 | 2016 |
Titles as the award lists print them; a title ending in "..." was cut short at import.
History, structure, leadership, locations and projects of Alhaj Hassan Group B.S.C Closed.
Haji Hassan Al A'ali starts a small manual stone-crushing plant near Burhama.
First manual block machine bought; crushing plant upgraded.
First group office opens on Lulu Road; a small tile plant is added.
Construction department set up; first reclamation job at Mina Salman and schools, clinics and hospitals built for the Public Works Department.
All plants moved to the Salmabad site.
Three-year crusher contract secured with Bahrain Petroleum Company (BAPCO).
First asphalt plant bought and Bahrain Asphalt set up as the first national asphalt contractor; first airport runway carried out.
Asphalt plant moved to Sitra; first phase of Jalal Garden housing compound opens.
Pavement works at the Mina Salman development; calcium silicate plant bought to make lightweight blocks.
Haji Hassan Readymix established; Bahrain Precast Concrete Co. formed as a joint venture.
Haji Hassan Mechanical Engineering Workshop established.
Crane division set up with a 400-ton crane; Delmon Shopping Centre opens.
Haji Hassan Reinforcement Co. acquired.
Arabian Parts Company established; blocks factory moved to Abu Zwaid; Haji Hassan Tower opens in Sanabis.
Arabian Chemical Industries (ISOLA) established.
Polythene tank factory established; United Precast Concrete (UPC) set up in Dubai; investment in Bahrain Rubber Co.
Al A'ali Shopping Complex opens in Seef; Bahrain Pipes Co. established; Bahrain Asphalt opens a Doha branch for sub-base and asphalt work on the Dukhan Highway as a subcontractor.
UPC Oman established.
UPC Qatar established.
HSBC partnership through an investment in the BPC Group.
KRAH Bahrain established as a joint venture.
Mobile crane capacity raised to 500 tons.
KRAH Bahrain fully acquired by the group.
New plant for Bahrain Blocks; Evolve Concrete established.
Aba'ad Construction WLL established.
Jasra Interchange - Loop 1 widening, Jasra, Bahrain - Contractor
Haji Hassan Readymix introduces flooring solutions.
Roads and asphalt contractor
Ready-mix concrete
Precast concrete (joint venture)
Concrete blocks and paving
Steel reinforcement
Crane hire
Pipes
Polythene tanks
Pipes
Insulation and construction chemicals
Parts
Property
Shopping centre, Seef
Concrete products
Construction
| Firm | Role | Founded |
|---|---|---|
| Bahrain Asphalt | Roads and asphalt contractor | 1965 |
| Haji Hassan Readymix | Ready-mix concrete | 1978 |
| Bahrain Precast Concrete | Precast concrete (joint venture) | 1978 |
| Bahrain Blocks | Concrete blocks and paving | |
| Haji Hassan Reinforcements | Steel reinforcement | 1981 |
| Haji Hassan Cranes | Crane hire | 1980 |
| Bahrain Pipes | Pipes | 1996 |
| Bahrain Tanks | Polythene tanks | 1993 |
| KRAH Bahrain | Pipes | 2011 |
| Isola Solutions W.L.L. | Insulation and construction chemicals | 1985 |
| Arabian Parts Company | Parts | 1984 |
| Haji Hassan Properties | Property | |
| Al A'ali Shopping Complex | Shopping centre, Seef | 1996 |
| Evolve | Concrete products | 2022 |
| Aba'ad Construction | Construction | 2023 |
Haji Hassan Bin Ali Al A'ali - Founder
Projects only · 4 projects
Projects only
Projects only · 1 project
Projects only
| Project | Country | Sector | Firm | Year | Detail |
|---|---|---|---|---|---|
| Dukhan Highway (west contract) - pavement works | Qatar | Roads | Bahrain Asphalt | 2009 | Paving of the new dual four-lane highway from Shahaniya to the Dukhan industrial area, January 2006 to July 2009, using two 240 t/h asphalt plants set up for the job. |
| Jasra Interchange - Loop 1 widening | Jasra, Bahrain | Roads | Bahrain Asphalt | 2023 | Completed April 2023. Included design-and-build micro-piling (300 mm contiguous micro piles) to protect the abutment of the existing bridge. |
| Jasra Interchange upgrade Phase 2 - precast bridge parapet barriers | Jasra, Bahrain | Roads | Bahrain Precast Concrete (BPC) | Part of the widening of Shaikh Isa Bin Salman Highway and the Jasra interchange upgrade. | |
| Zallaq cycle tracks (sections A-B-C and C-D) | Zallaq, Bahrain | Roads | Bahrain Asphalt | Embankment, sub-base preparation, asphalt layers, signs and road marking along Al Zallaq Highway and Gulf of Bahrain Avenue. | |
| South Bahrain loop road Stage 2 (Tunnel J) | Bahrain | Roads | Bahrain Asphalt | Demolition of the existing carriageway, storm water drainage network, raising of the main road and a cast in-situ concrete underpass. |