Société des Ciments d'Aïn El Kebira (SCAEK) logo

Société des Ciments d'Aïn El Kebira (SCAEK)

Overview

Société des Ciments d'Aïn El Kebira (SCAEK) is an Algerian cement maker in the wilaya of Sétif. It is a joint-stock company wholly owned by the state group GICA, with share capital of DZD 2.2bn.

Its plant sits on a 50 ha site about 20 km north-east of Sétif and 7 km south of Aïn El Kebira, next to a limestone quarry with long-term reserves. Two production lines give an installed capacity of 3 million tonnes of cement a year. It currently makes CEM II/A 42.5 Portland composite cement and CEM I 42.5 sulphate-resisting cement, and can also produce CPA 52.5, CPJ 32.5 and oil-well cement. Head office is in the Bounechada district of Sétif.

Company type

RoleSupplier
Legal formSPA (société par actions)
SectorsCement
ServicesCement production and sales (CEM II/A 42.5, CEM I 42.5 ES sulphate-resisting; CPA 52.5, CPJ 32.5 and oil-well cement on demand)

Key facts

Capacity3 million tonnes of cement a year, 2 production lines
Site50 ha plant, 20 km north-east of Sétif
Share capitalDZD 2,200,000,000
ParentGICA (100%)
CertificationsISO 9001:2015, ISO 14001 (AFAQ AFNOR); TEDJ conformity mark for CEM II/A-P 42.5 N (NA 442)
QuarryAbout 220 ha, Djebel Medjounes limestone and Theniet Moloutou marl; reserves estimated at 100+ years

Projects

Scroll the table sideways to see every column.

ProjectLocationYearClientRoleScaleSectorStatus
Ain El Kebira cement plant second lineAin El Kebira, Setif, Algeria2017SCAEKOwner - contractor Polysius SAS (France)2 million t/yrCementCompleted

Official registrations and listings

  • Algerian state group subsidiaries (GICA, Cosider, Sonatrach, Sonelgaz), from the group sites

    GICA group companies

    See the list · Checked 21 Nov 2026

  • GICA (Groupe Industriel des Ciments d'Algérie), group site

    GICA group companies

    Listed asSociété des Ciments d'Aïn El Kebira (SCAEK)

    See the list · Checked 21 Nov 2026

Company detail

History of Société des Ciments d'Aïn El Kebira (SCAEK).

History

  1. project

    State building materials company SNMC signed the contract for the Ain El Kebira cement line, with a 45-month build period

  2. project

    Provisional acceptance of the first line

  3. milestone

    First 1 million tonne a year line entered production

  4. strategy

    SNMC restructured into four regional cement groups (East, West, Centre, Chlef)

  5. strategy

    Restructured as a subsidiary of the eastern cement group ERCE

  6. deal

    Became a subsidiary of GICA after ERCE was dissolved

  7. project

    Signed contract with Polysius SAS (France) for a second production line

  8. project

    Second-line contract came into force

  9. expansion

    Second line of 2 million tonnes a year entered production, lifting capacity to 3 million tonnes

  10. project

    Ain El Kebira cement plant second line, Ain El Kebira, Setif, Algeria - Owner - contractor Polysius SAS (France)

Sources

  1. SCAEK - Société des Ciments d'Aïn El Kebira (SCAEK), read 22 Nov 2026
  2. Présentation - Société des Ciments d'Aïn El Kebira (SCAEK), read 22 Nov 2026
  3. Société des Ciments d'Aïn El Kebira (SCAEK) - GICA, read 22 Nov 2026
  4. Presentation de la Societe des Ciments de Ain El Kebira - SCAEK, read 23 Nov 2026
  5. Certifications - SCAEK, read 23 Nov 2026

Similar companies

See all construction suppliers in Algeria