PowerChina
Location
Abu Dhabi, UAEOverview
PowerChina is classed in the directory as a main contractor based in Abu Dhabi, UAE. Headquartered in Beijing, China; UAE office in Abu Dhabi. Its earliest dated listing in the records we hold is from 2025.
It is named on 6 contract awards in public announcements, most recently in 2026. It is named as the client on one contract award.
Company type
| Role | Main contractor |
Key facts
| Earliest dated listing | 2025 |
| Based in | Abu Dhabi, UAE |
| Contracts named | 6 (latest 2026) |
Contracts and awards
| Contract | Scope | Awarded by | Role | Value | Date | Status | Source |
|---|---|---|---|---|---|---|---|
| Round-the-clock 5.2GW solar PV + 19GWh BESS (1GW baseload) | EPC of northern block: 2.1GWdc PV, 7.75GWh BESS, substations | Masdar (with EWEC) | EPC | c. AED 6,978mUSD 1.9bn | 23 Mar 2026 | Checked | Masdar, MEED |
| Round-the-clock solar PV + storage, Mshayrif - North block (2.1GW PV, 7.75GWh) | EPC for northern block of 5.2GW PV + 19GWh BESS project | Masdar (with EWEC) | JV member - PowerChina / Huadong Engineering | c. AED 6,978mUSD 1.9bn | 12 Mar 2026 | Checked | Yicai, MEED |
| 24/7 solar PV and BESS gigascale project, northern block (2.1GW DC PV, 7.75GWh BESS) | Masdar-EWEC round-the-clock solar+storage in Abu Dhabi, up to 1 GW baseload - 5.2 GW DC PV + 19 GWh BESS; PowerChina EPC LoA 17 Jan 2025 (shared with L&T) | Masdar (with EWEC) | EPC | c. AED 6,977.8mUSD 1.9bn | 12 Mar 2026 | Checked | Shanghai Stock Exchange news release, MEED (teaser visible, paywalled) |
| Hafeet Rail logistics facilities Al Buraimi and Sohar | Hafeet Rail (UAE-Oman, ~US$2.5bn) cargo handling - Logistics facilities at Al Buraimi and Sohar for bulk, container, breakbulk cargo; Sohar loco/wagon maintenance | Hafeet Rail | JV member - Larsen & Toubro / PowerChina JV | - | 7 Feb 2025 | Checked | MEED (teaser), Enterprise, AGBI, Zawya |
| Masdar-EWEC round-the-clock 5.2GW solar PV + 19GWh BESS - south site | Masdar-EWEC round-the-clock solar+storage in Abu Dhabi, up to 1 GW baseload - 5.2 GW DC PV + 19 GWh BESS; PowerChina preferred EPC, LoA 17 Jan 2025 | Masdar (RTC project company with EWEC) | EPC | - | 17 Jan 2025 | Checked | Masdar, MEED (teaser), TaiyangNews, SaudiGulf Projects |
| 19GWh RTC solar + BESS project | Masdar-EWEC round-the-clock solar+storage in Abu Dhabi, up to 1 GW baseload - 5.2 GW DC PV + 19 GWh BESS; EPC letters of award 17 Jan 2025 | Masdar (with EWEC offtake) | JV member - Larsen & Toubro / PowerChina consortium | c. AED 22,035mUSD 6bn | 2025 | Unconfirmed | MEED |
Contracts awarded
| Contract | Scope | Contractor | Role | Value | Date | Status | Source |
|---|---|---|---|---|---|---|---|
| Al Ajban 1.5GW solar PV | Tracker supply | Arctech | supplier | - | 3 Jan 2025 | Unconfirmed | SaudiGulf Projects |
From public announcements, stock exchange filings and press; values as announced.